Prime Minister Balen Shah and Indian Prime Minister Narendra Modi are scheduled to jointly lay the foundation stone for the Lower Arun Hydropower Project on Monday, November 23, 2026. The ceremony will be conducted digitally from New Delhi.
Project Details
The 669 MW project is being developed by SJVN Lower Arun Power Development Company (SLPDC), a subsidiary of India’s state-owned Satluj Jal Vidyut Nigam (SJVN). The project’s main structures will be located in Chichila Rural Municipality and Khandbari Municipality in Sankhuwasabha district. The estimated cost of the project is Rs 92.67 billion, with the Indian government approving an investment of approximately Rs 91 billion. This marks one of the largest foreign investments in Nepal, with an estimated cost of $1.3 billion USD.
The project will involve the construction of tunnels, shafts, and a powerhouse. Patel Engineering Limited has secured a contract worth Rs 15.93 billion for Package 2, which includes civil and hydro-mechanical works, with a completion period of 54 months. The project is expected to generate 2901 million units of electricity annually. Upon commercial operation, 21 percent of the total electricity produced, equivalent to 197.1 MW, will be provided to Nepal free of charge. After 25 years of commercial operation, the project will be handed over to the government in operational condition.
Land Acquisition and Compensation
A total of 268 households will be directly affected by the project, with 16 households facing complete displacement. Approximately 65 hectares of private land, 70 hectares of forest land, and 6 hectares of public land will be acquired for the project. So far, Rs 999.839 million in compensation has been distributed to approximately 253 affected families. The project plans to distribute a total of Rs 1.40 billion in compensation to 656 individuals whose land falls within the construction site. Land valuations in the affected areas range from Rs 500,000 to Rs 3.4 million.
Background
SJVN was selected to develop the Lower Arun Hydropower Project through an international competitive bidding process in January 2021. A Memorandum of Understanding (MoU) was signed between Nepal’s Investment Board and SJVN Limited on July 11, 2021. SJVN Lower Arun Power Development Company (SLPDC) was registered in Nepal on May 26, 2023, for project implementation. The Project Development Agreement (PDA) between the Investment Board Nepal and SLPDC was signed on June 1, 2023. The Indian Cabinet Committee on Economic Affairs approved an investment of INR 5,792.36 crore (approximately NPR 91 billion) for the project on August 2, 2024. Compensation distribution to project-affected individuals in Sankhuwasabha began on October 30, 2024.
Future Outlook
The construction period for the project is estimated to be five years. The surplus electricity generated from the project will be exported to India.
Open Questions
It remains unclear what other agreements or understandings will be signed during Prime Minister Balen Shah’s visit to India. Further details regarding the detailed schedule of the foundation stone laying ceremony and the participation of other officials are not yet available.