Madhesh Will Revolt If Sun Koshi-Marin Diversion Contract Cancelled, Warns MP Jha

National Independent Party MP Manish Jha has warned that the Madhesh region will revolt if the Sun Koshi-Marin Diversion project contract is cancelled, urging the government for a clear action plan.
Nmkhabar English Desk
3 min read
Size:
Madhesh Will Revolt If Sun Koshi-Marin Diversion Contract Cancelled, Warns MP Jha
Share:

National Independent Party (RSP) lawmaker Manish Jha has warned that the Madhesh region will erupt in protest if the contract for the Sun Koshi-Marin Diversion multipurpose project is cancelled. Speaking at a Public Accounts Committee meeting on Tuesday, Jha demanded a clear action plan from the government to ensure the project is completed as planned, rather than being abandoned.

Project Significance and Delays

The Sun Koshi-Marin Diversion project is crucial for agriculture and irrigation in five districts of the Madhesh province, aiming to provide irrigation to approximately 180,000 bighas of land. Jha expressed dissatisfaction with the delays, noting that while the 13.3-kilometer tunnel was ‘breakthrough’ in May 2024, the construction of the dam and other structures has not gained momentum.

“If this project is cancelled, there will be no option but for Madhesh to revolt,” Jha stated. He emphasized the need for the government to clarify the reasons for the delay, assess the potential economic and agricultural losses, and outline future plans for the project.

Advertisement

The lawmaker highlighted the lost opportunities for farmers due to the lack of irrigation, questioning the accountability for the uncultivated land and potential yield. “How much cultivation could have happened if 180,000 bighas had received water? How much would have been produced?” he asked, demanding clarity on the reasons for the project’s halt.

Contract Cancellation and Committee Action

The Public Accounts Committee has directed the Ministry of Energy, Water Resources and Irrigation to provide necessary documents within seven days regarding the cancellation of the project’s contract. The directive came after discussions with officials including Dinesh Rajauria, director-general of the Department of Water Resources and Irrigation.

An complaint filed with the committee stated that the contract was cancelled at the last moment, after all stages of the bidding process were completed and the financial proposals were ready to be opened. The complainant claims that the cancellation has caused financial losses to the state and further delayed the project’s construction.

However, Dinesh Rajauria asserted that the decision to cancel the contract was lawful. Sushil Acharya, a joint secretary at the Ministry of Energy, stated that cancelling one bid and proceeding to another bid process does not necessarily result in significant financial loss, and the cost might even decrease in the re-bidding process.

Background and Future Steps

The Sun Koshi-Marin Diversion project was declared a national pride project on January 20, 2020. Tunnel excavation began in October 2022. The contract was reportedly cancelled in the second week of November based on a provision in the Public Procurement Act, 2063.

The Ministry of Energy, Water Resources and Irrigation is preparing to re-issue tenders to move forward with the project. The project is planned for completion by October 2025.

Open Questions

The exact reasons for the contract cancellation remain unclear. While complainants cite procedural errors and potential financial losses, the director-general maintains the decision was lawful. Investigations are ongoing to ascertain if there was any political or administrative interference in the decision to cancel the contract. Allegations that the Prime Minister’s secretariat influenced the cancellation by having Director-General Rajauria taken into police custody have not been verified.

What happens next

The Public Accounts Committee will study the documents and proceed with further discussions.

Official sources (1) View
Advertisement
Nmkhabar English Desk

Nmkhabar English Desk

Correspondent · Nmkhabar

NM Khabar English desk. Stories are prepared with AI assistance and checked against their sources — how we work: https://nmkhabar.com/ai-policy/ . Report an error: info@nmkhabar.com

More news