India has announced the completion of the Final Location Survey (FLS) for the proposed Raxaul-Kathmandu electric broad gauge railway. The announcement was made on Monday, November 25, 2024, by Indian Prime Minister Narendra Modi and Nepal’s Prime Minister Pushpa Kamal Dahal in a joint press release issued from Hyderabad House in New Delhi.
Project Details and Cost
The estimated cost for this railway project is approximately Rs 4.5 trillion. The total length of the proposed railway line will be 136 kilometers, with a significant portion, around 42 kilometers, requiring tunnel construction. This tunnel section represents about 30 percent of the total route. The project also proposes the construction of 124 large bridges. The maximum speed for trains on this route is proposed to be 120 kilometers per hour.
The land required for the railway construction is estimated at 1478.200 hectares, of which 580 hectares will be private land requiring acquisition. Compensation for private land alone is estimated to cost Rs 27.24 billion Indian Rupees. The project’s financial rate of return is projected at 4.81 percent, with an economic rate of return of 14.06 percent.
Cost estimates for the project have increased over the years. A preliminary engineering and traffic (PET) survey in 2019 estimated the cost at around Rs 2.5 trillion. By 2022, this estimate rose to Rs 3.2 trillion. The current estimate stands at approximately Rs 4.5 trillion, with projections suggesting it could reach Rs 5 trillion due to inflation.
Impact on Madhesh Province
The railway line will commence from Raxaul, pass through Birgunj, and extend to Nijgadh, before reaching Kathmandu’s Chovar. This route is expected to facilitate the transportation of both passengers and goods from the border areas to the Kathmandu Valley. The railway’s passage through Birgunj, known as an economic hub, will provide a crucial link for transporting not only imported goods from India but also industrial products from the Birgunj-Simara industrial corridor and eastern and central Nepal to Kathmandu via Nijgadh. This is anticipated to reduce transportation costs and enhance market competitiveness.
Background and Future Steps
The study process for the Kathmandu-Raxaul railway began after Indian Prime Minister Narendra Modi’s visit to Nepal in 2016. India submitted the PET survey report in 2018. A bilateral Memorandum of Understanding (MoU) to proceed with the FLS was signed in October 2021. The FLS was conducted by India’s Konkan Railway Corporation Limited (KRCL) within the stipulated 18 months. India handed over the FLS report to the Nepali government on July 20, 2023.
The journey from Raxaul to Kathmandu, which currently takes 6 to 8 hours by road, is expected to be reduced to approximately 2.5 hours once the railway is operational.
The first railway service in Nepal began in 1927 as the ‘Nepal Government Railway,’ connecting Amlekhgunj with Raxaul, a distance of 47 kilometers. This service was discontinued in 1974.
What happens next
Following the submission of the report, the Nepali government will review it and provide its feedback. Based on Nepal's response, the report will be finalized, and India will hand over the final report to Nepal. The project will move forward practically only after the approval of the Nepali government.